The Monterey County Rail Extension Project will extend passenger rail service from Santa Clara County south to Salinas. TAMC is pursuing a phased implementation of the Project. Phase 1, known as the Kick Start Project, includes Salinas train station circulation improvements, a train layover facility in Salinas, and track improvements at the Gilroy station and between Salinas and Gilroy. The Kick Start Project is proceeding with wrapping up construction of Package 1, improvements at the Salinas train station. The layover facility (Package 2) and track improvements (Package 3) are now in final design.
Construction of Package 1: Salinas Station Improvements
TAMC hired Monterey Peninsula Engineering (MPE) for construction of Package 1, MNS Engineers as Construction Managers on the project, and HDR Engineering to provide design support during construction. In May 2021, the construction team worked to close out the Caltrans, stormwater, and Salinas permits. The stormwater permit was closed out on April 26. As-built plans were provided to Caltrans and Salinas to close out their permits. Once the permits have been closed, remaining work is landscaping maintenance through December 2021.
TAMC staff is coordinating with Caltrans and the City of Salinas on the logistics to transfer ownership of the completed project to the City, pursuant to the adopted Memorandum of Understanding. The land transfer must be approved by the California Transportation Commission (CTC) prior to the City and TAMC approving transfer agreements. The CTC is requiring the City to commit to replacing any parking spaces used for future development in a location walking distance from the station.
Property Acquisition for Package 2: Salinas Layover Facility
On December 4, 2019, the Transportation Agency Board approved Resolutions of Necessity on portions of four parcels and one full parcel needed for the Salinas layover facility. TAMC staff has received the deed for one parcel and continues to oversee the right-of-way consulting team of AR/WS and Meyers Nave to further negotiations and finalize the remaining acquisitions.
Final Design for Package 2 and Package 3: Gilroy Station & Track Improvements; Operations Scenarios
The final design team held the following meetings to further the project's design:
- Caltrans and Caltrain - May 19 and 27
- City of Salinas - May 5, 19, and 26
- City of Gilroy - May 10
- Northern California Rail Working Group - May 13