Item Coversheet

Agenda Item 5.

TAMC Logo     
TRANSPORTATION AGENCY FOR MONTEREY COUNTY
Memorandum
To: 

Rail Policy Committee

From:

Christina Watson, Director of Planning

Meeting Date:

November 1, 2021

Subject:

Salinas Rail Kick Start Project Update



RECOMMENDED ACTION:

RECEIVE update on the Salinas Rail Kick Start project.

SUMMARY:

Activities on the Salinas Rail Kick Start project since the last update in September include work related to closing out permits for the construction of Package 1 (Salinas Station access and circulation improvements) and coordination efforts with key stakeholders on Packages 2 (Salinas layover facility) and 3 (Gilroy track connections).

FINANCIAL IMPACT:

The capital cost of the Monterey County Rail Extension project, Phase 1, Salinas Kick Start project (the Salinas station and improvements in Santa Clara County), is estimated at $81 million. The Kick Start project is proceeding with secured state funding under the adopted state environmental clearance.  

 

Package 1 is under construction by MPE Engineering for an original contract amount of $7,487,989 with a contingency fund of $1,123,200. Approved change orders to date total $809,641.69, or 72.1% of the contingency fund approved by the Board.

DISCUSSION:

The Monterey County Rail Extension Project will extend passenger rail service from Santa Clara County south to Salinas. TAMC is pursuing a phased implementation of the Project. Phase 1, known as the Kick Start Project, includes Salinas train station circulation improvements, a train layover facility in Salinas, and track improvements at the Gilroy station and between Salinas and Gilroy. The Kick Start Project is wrapping up construction of Package 1, improvements at the Salinas train station. The layover facility (Package 2) and track improvements (Package 3) are now in final design.

 

Construction of Package 1:  Salinas Station Improvements

 

TAMC hired Monterey Peninsula Engineering (MPE) for construction of Package 1, MNS Engineers as Construction Managers on the project, and HDR Engineering to provide design support during construction. In October 2021, the construction team worked to close out the Caltrans and Salinas permits. Once the permits have been closed, remaining work is landscaping maintenance through December 2021. Staff will bring a project close-out report to the TAMC Board in December.

 

TAMC staff is coordinating with Caltrans and the City of Salinas on the logistics to transfer ownership of the completed project to the City, pursuant to the adopted Memorandum of Understanding. The land transfer must be approved by the California Transportation Commission (CTC) to empower the City and TAMC to approve transfer agreements. The CTC is requiring the City to commit to replacing any parking spaces used for future development in a location walking distance from the station.

 

Property Acquisition for Package 2: Salinas Layover Facility

 

On December 4, 2019, the Transportation Agency Board approved Resolutions of Necessity on portions of four parcels and one full parcel needed for the Salinas layover facility. TAMC staff continues to oversee the right-of-way consulting team of AR/WS and Meyers Nave to further negotiations and finalize the remaining acquisitions. A request for proposals for a team to assist in the negotiations regarding Union Pacific Railroad parcels in Gilroy and Salinas has a deadline of October 28.

 

Final Design for Package 2 and Package 3: Gilroy Station & Track Improvements; Operations Scenarios 

 

The final design team held the following meetings to further the project's design:

  • Caltrans and Caltrain - October 8 and 19
  • City of Salinas - October 27
  • Santa Clara Valley Transportation Authority (VTA) and City of Gilroy - October 11
  • Union Pacific and Caltrans - October 15

 

Documents the team is preparing for future Committee/Board approval include the following:

  • Memorandum of Understanding between TAMC and Caltrain outlining the process towards an operating agreement.
  • Memorandum of Understanding among TAMC, VTA and Gilroy for improvements near the Gilroy train station to support the extension of passenger rail service south from Gilroy.
  • Package 1 construction contract close-out report.
  • Contract extension for MNS Engineers, whose Construction Management contract, which includes all three construction packages, expires 12/31/21.