TAMC is planning for the extension of rail service from Santa Clara County to Monterey County, known as the “Salinas Rail Extension Project”. This project extends passenger rail service from Santa Clara County south to Salinas (68 miles). TAMC is currently pursuing a first phase of the Salinas Rail Extension Project, called the “Kick Start Project”. The Kick-Start project includes improvements at the Salinas Station, a two-train layover facility in Salinas, improvements to the Union-Pacific-owned Coast Main Line track between Gilroy and Salinas, track improvements in Gilroy to allow for run-through service, and minor improvements to the Gilroy, Morgan Hill and San Jose Tamien stations.
Approval of this action will allow TAMC to request proposals from qualified consultants for the construction management of the Kick Start project.
Online as a Web Attachment is the draft scope of work for the Request for Proposals, subject to review and approval by Agency counsel. The tasks under this contract include the review of the 75% and 100% designs and bid documents, oversight of structure demolition (demolition itself will be a separate contract), oversight of utility relocations, and finally construction oversight.
The RFP schedule is proposed as follows:
Date/ Timeframe Task
June 28, 2017 Release RFP
July 7, 2017 Questions Due
July 14, 2017 Revised RFP released (if necessary)
August 4, 2017 Proposals Due
August 5-11, 2017 Sub-committee review and ranking of submittals
August 14-21, 2017 Interviews, if necessary
August 24, 2017 Staff recommendation to the Rail Policy Committee
September 11, 2017 Rail Policy Committee recommendation to TAMC Board
September 27, 2017 TAMC Board approval of consultant contract
September 27-October 6, 2017 Circulate contract for signatures; issue Notice to Proceed
October 2017 Kick-off meeting